Plant 7 of Halcón Cerámicas has two production levels with different types of kilns and vertical dryers. The original configuration of the heat recovery system did not allow for efficient use of the thermal energy generated, which affected both the performance of the dryers and the overall energy consumption of the plant.
Initial situation
Two double-channel kilns that fed six vertical dryers through heat recovery.
Two single-channel kilns in the adjacent plant, without waste heat utilization.
Unbalanced air distribution (Excess pressure in the first dryers and lack of hot air in the last ones.)
Insufficient heat recovery in the dryers of the adjoining plant.
Problems detected
— Low dryer performance due to poor hot air distribution.
— Loss of thermal energy generated by the single-channel kilns.
— Existing recovery system was poorly optimized, despite being based on a solution widely installed in the sector.
Solution implemented
Results obtained
- Significant increase in energy utilization from the kilns.
- Improved operation and stability of all dryers.
- Higher energy savings than those obtained with the previous system.
- Amortization of the renovation and the new installation in less than a year, thanks to the CAES system.